Skip to content

Benton County, Tennessee (Benton): West Camden Sanitary Landfill (Waste Management of Tennessee, Inc.)

    DIVISION:

    Contracting

    ROLE:

    General Contractor

    OWNER:

    Hoover Mason Recycling

    CONTRACT VALUE:

    COMPLETION DATE:

    Phase 2 involved construction of a 10 acre lined cell.  The project consisted of excavation to subgrade of approximately 100,000 cubic yards of soil, 3,000 cubic yards of rock, placement of 55,000 cubic yards of geologic buffer, a 2’ thick clay liner system consisting of 33,000 cubic yards, installation of geomembrane liner by others, and placement of protective cover material comprised of 29,000 cubic yards of granular drainage material and 4,500 cubic yards of soil material. The leachate collection system entailed 1,500 linear feet of 6” SDR 11 HDPE pipe, 1,500 linear feet of 8” SDR 11 HDPE pipe, approximately 70 linear feet of 18” HDPE sump riser pipes, and 100 linear feet of leachate force main. Ancillary items include roadway construction, borrow area development, stormwater system upgrades, and permanent seeding. 

    Celebrating Our 60th Anniversary!

    X